Contingency Reserves on Ground-Up Construction Loans: Why 10% of the Budget Gets Held Back
Your framing subcontractor’s bid comes in $38,000 over the number in your original scope of work. If your ground-up construction loan has no contingency reserve built into the budget, that $38,000 comes out of your pocket today, before the next draw funds. If the loan has one, it might come out of the project instead.
Most first-time ground-up borrowers find out which situation they’re in only after the overrun hits. By then it’s too late to negotiate the reserve into the deal.
What a contingency reserve actually is
On a ground-up construction loan, we don’t release 100% of the construction budget for you to spend on whatever line item runs hot. A piece of the hard construction cost budget — typically 5% to 10%, sized to the scope’s complexity and your experience — sits inside the total loan amount but is held back from the regular draw schedule. It only gets released against a documented cost overrun: a change order, a site condition nobody could see until excavation, a material cost spike between bid and pour.
That holdback structure doesn’t exist on a fix-and-flip rehab loan, where draws release money as rehab work gets completed with no separate reserve carved out, and it has no equivalent at all on a DSCR rental loan, which has no draw schedule in the first place. It’s specific to the risk profile of building something from a slab up.
The arithmetic: how a $900,000 budget turns into $90,000 you can’t touch
Say your scope of work totals $900,000 in hard construction costs — foundation through final inspection — on a lot you already own free and clear, inside a business entity. At a 10% contingency, $90,000 of that budget is set aside at closing. The remaining $810,000 is what actually moves through your draw schedule as the slab, framing, mechanicals and finishes get inspected and verified.
| Line item | Amount |
|---|---|
| Total hard construction budget | $900,000 |
| Contingency reserve held back (10%) | $90,000 |
| Budget released through regular draws | $810,000 |
Now the framing bid comes in $38,000 over scope. You don’t get to simply ask for a bigger draw. We need a change order, an updated budget showing where the extra cost lives, and confirmation the remaining contingency still covers what’s left of the build. Assuming it does, $38,000 moves from the reserve into the draw schedule, leaving $52,000 of contingency to cover anything else that comes up before the certificate of occupancy.
Who’s personally on the hook if the money runs out
Our ground-up construction program sets a 650 minimum FICO and requires at least three completed real estate deals, including one prior ground-up build — that experience bar exists specifically because contingency math only works when the person running the job has already watched a budget blow through its buffer and knows how to manage it. On top of credit and experience, the loan typically carries a completion guaranty: your personal commitment, outside the entity that holds title, that the project actually gets finished, not just that the loan gets serviced. A contingency reserve absorbs the first overrun. A completion guaranty is what’s behind the deal if the reserve runs out before the roof goes on.
What happens when the contingency isn’t enough
It happens — a foundation hits rock nobody flagged in the soil report, or lumber prices move between your bid and your pour. When a documented overrun exceeds what’s left in the reserve, the loan doesn’t just expand to cover it. You’re generally looking at one of three outcomes: inject cash to close the gap and keep the draw schedule moving, get the general contractor to value-engineer the remaining scope back down to what’s left in the budget, or, in a severe case, pause draws while the budget gets fully re-underwritten. None of those is fast, which is exactly why the reserve exists — most overruns are small enough that it absorbs them without anyone noticing a delay.
When this is the wrong call
If your scope of work is still soft — a teardown-and-rebuild on a lot with an old structure whose foundation condition is unknown, or a site where the soil report is preliminary — a standard 5–10% contingency may not be the right tool. In that situation, the honest move is to get a firmer scope of work and updated bids before you close, not to lean on the reserve to cover what should have been priced in up front. A contingency reserve is built to absorb normal construction surprises on a well-scoped project. It is not a substitute for a scope of work that was rushed to get a loan approved, and treating it that way is how a manageable overrun turns into a stalled project.
All figures above are indicative examples only and subject to underwriting and credit approval — your actual contingency percentage, experience requirements and guaranty terms depend on the deal. If you’re putting together a ground-up build and want to know how a reserve would size against your real budget, our ground-up construction program page has the full underwriting criteria, and our current rates page shows where construction pricing sits today. For the other property types and strategies we finance, see our loan programs overview, which covers fix-and-flip, bridge, DSCR and multifamily. Ready to put a deal in front of us? Submit the deal and we’ll tell you how the budget and the reserve pencil out.