Mechanic’s Liens on a Fix-and-Flip or Ground-Up Loan: How a Subcontractor Can Jump Ahead of Your Lender
A framing crew finishes a ground-up build outside Jacksonville. The general contractor gets paid on the draw, but the framing sub doesn’t see his $34,000 share of it. Three weeks later, a Claim of Lien shows up on the property’s title, recorded against your project, not against the GC’s bank account. Your buyer’s closing attorney flags it the same week you’re trying to schedule the sale. That lien is now sitting on the chain of title ahead of the payoff you were counting on, and nobody is funding a sale until it’s gone.
This happens on fix-and-flip and ground-up construction deals more than most investors expect, and it’s rarely the general contractor who files. It’s almost always a sub or supplier who never got a direct payment and never signed a waiver.
Why a lien can out-rank the loan securing the property
Most states run mechanic’s liens on a “relation back” theory: the lien’s priority doesn’t date from the day it’s recorded, it dates back to the day work first started on the project (or in some states, the day the subcontract was signed). That means a lien recorded in month eight of a nine-month build can legally jump ahead of a mortgage or deed of trust recorded in month one, if the lien relates back to a start date that predates the loan’s recording. Lenders manage this risk with title insurance endorsements and draw controls, not by hoping it doesn’t happen.
Florida’s Notice of Commencement: a step that changes your exposure
In Florida, Chapter 713 (the Construction Lien Law) requires the property owner to record a Notice of Commencement before work begins on any direct contract over $2,500, and to post a certified copy at the job site where permits are displayed. Skip it, and a lender funding draws without confirming the NOC is on file can be forced to re-pay subs directly even after paying the GC once. A lienor generally has 90 days from the date they last furnished labor or materials to record a Claim of Lien, and one year from recording to file suit to enforce it. None of those numbers are universal. Texas ties its mechanic’s lien and retainage rules to different notice deadlines tied to the month work was performed, and California requires most subcontractors to serve a Preliminary Notice within 20 days of starting work just to preserve lien rights at all. Treat the Florida NOC threshold and the 90-day/one-year windows above as Florida-specific, not a national rule.
The arithmetic: what clearing a lien actually costs
Say that $34,000 framing lien is real and the sub’s claim is valid. You have three ways to clear it before closing, and they don’t cost the same:
- Pay it directly. $34,000, plus whatever you already paid the GC for that same scope — if the GC pocketed the draw instead of paying the sub, you may be paying for the same work twice.
- Bond it off. Most states let you discharge the lien from title by posting a surety bond, typically 150% of the claim, so roughly $51,000 in bond value to clear a $34,000 lien, while the dispute over whether the sub is actually owed the money gets resolved separately. The bond premium itself usually runs 1–3% of the bond amount, so $500–$1,500 in actual cash outlay, but it ties up that collateral until the claim resolves.
- Litigate it. Cheapest if the lien is invalid (wrong amount, missed a notice deadline, filed against the wrong legal description), but slowest — and your closing doesn’t wait for a court date.
Bonding off is almost always the fastest path to a closeable title when the sale date is fixed and the dispute isn’t.
How draws are structured to keep this from happening
On our fix-and-flip and ground-up construction programs, draws are released against verified progress, and lien waivers are part of that verification, not an afterthought. A conditional waiver is signed when a sub is paid but hasn’t cashed the check yet; an unconditional waiver is signed once funds have cleared. Partial waivers cover the draw just paid; a final waiver, collected at completion, covers the whole scope.
| Waiver type | When it’s signed | What it protects |
|---|---|---|
| Conditional partial | At draw disbursement, before funds clear | This draw only, contingent on payment clearing |
| Unconditional partial | After funds clear | This draw only, no contingency |
| Conditional final | At project completion, before final payment clears | Entire contract scope, contingent on clearing |
| Unconditional final | After final payment clears | Entire contract scope, no contingency |
On a deal with a single GC and two or three subs, waivers collected at each draw are usually enough. The exposure above comes from a GC who collects a draw and doesn’t pass the money down the chain — which waivers alone don’t stop, because the sub never signed one for a draw they weren’t paid from.
When this is the wrong call
Waivers alone are the wrong control on a larger ground-up build with a long sub list — a dozen-plus subcontractors, multiple tiers of sub-subs, and a GC you haven’t worked with before. On those deals, joint checks (payable to the GC and the specific sub together) or a title company construction escrow that disburses directly to subs on verified invoices is worth the extra coordination. It’s slower per draw, but it removes the single point of failure where one GC decides who actually gets paid. If your project fits that profile and your current draw process is “pay the GC and trust the waiver,” that’s the gap to fix before the next draw, not after a lien shows up.
If a lien already shows up on title
Don’t ignore it and hope it expires — most states give lienors a year or more to enforce, well past your intended closing date. Get the recorded claim to your closing attorney immediately, confirm the amount and the work described actually match what was performed, and price out bonding it off in parallel with negotiating a payoff. A title company that’s handled construction liens before can usually quote bond cost same-day.
Figures above are indicative, tied to Florida’s current statute and typical bond pricing, and are not legal advice — lien law is state-specific and fact-specific, so confirm current requirements with a construction attorney licensed in the property’s state. Financing is business-purpose only, for non-owner-occupied investment property held in a business entity, and every loan is subject to underwriting and credit approval. Our fix-and-flip loan programs and ground-up construction loans both use draw-based funding with lien-waiver controls built into the process; borrower-side waiver templates are available on our borrower forms page, and common questions about draws and title are covered in our FAQ.